电力 · 磅清扬 · 3789

国家太阳能园区项目(ADB 51182)

电网位置

加载电网数据…
2026
© OpenStreetMap contributors
规模—
总投资26.71 百万美元
工期3 年批准 → 关账
出资方—

工程量与造价构成(BOQ 1 行)

1 项工程 · 清单合计 11746.06 亿美元(来自项目文件的成本估算/工程量清单,金额为原文币种原值,非全部口径,可能与总投资不等)

光伏园区基础设施小计(ADB 51182)1 行 · 小计 1.17 百万美元
项目(原文)数量金额
光伏园区基础设施小计11.5km laterite road, 75m bridge, fence, drainage · 2018 · 51182-001-pam-en_11 lot1.17 百万美元

在同类电力项目中的位置

总投资

本项目 26.71
25.44中间值 4061.2
百万美元 · 灰点为同类项目,色带为常见范围

工期(批准 → 关账)

本项目 3
2中间值 36
年 · 灰点为同类项目,色带为常见范围

原文(6)

地点Kampong Chhnang
“The Project comprises the following outputs: Output 1: Construction of solar park and transmission interconnection The Project will support EDC in constructing a 100 megawatt solar power park in Kompong Chhnang Province and a transmission i…”
51182-001-apfs-en.txt · 第 11 页
电压等级230 kV
“t The 230kV Transmission Line Prepared by Electricité Du Cambodge (EDC) for the Asian Development Bank (ADB)”
51182-001-rp-en_5.txt · 第 1 页
变电容量50 MVA
“z • 2 (+2) Transformers:50MVA (ONAN) / 60MVA 31.5kA,1Sec (ONAF) each • Indoor type 22kV switchboard feeders ü Solar PV connection for individual IPP´s T1, 115/22kV T2, 115/22kV 50/60MVA 50/60MVA ü Storage ONAN/ONAF ONAN/ONAF Space for addit…”
51182-001-iee-en_0.txt · 第 40 页
批准2019
“8 Date of Board approval 23 May 2019 23 May 2019 23 May 2019 Date of loan agreement 28 June 2019 28 June 2019 28 June 2019 Date of loan effectiveness – In loan agreement 26 September 2019 26 September 2019 26 September 2019 – Actual 18 Sept…”
51182-001-pcr-en.txt · 第 5 页
生效2019
“t were declared effective on 18 September 2019, 10 days ahead of the schedule envisaged at loan and grant signing”
51182-001-pcr-en.txt · 第 13 页
开工2019
“s Indicative implementation period July 2019–June 2021 Executing agency Electricite du Cambodge Implementing agencies Electricite du Cambodge Consultants To be selected and engaged by the Asian Development Bank Firm: Quality and cost- Inter…”
51182-001-tar-en.txt · 第 8 页

其他信息:项目编号 3789 · 原定关账 30.0 · 实际关账 2022 · 总投资 26.71 · 融资结构 7.64

同类项目