Resettlement impacts affected households2012 · Table Results of Resettlement
1311 household
0 百万美元
[34390] Land acquired for towers and poles1 行 · 小计 —
项目(原文)
数量
金额
Land acquired for towers and poles2012 · Table Results of Resettlement
64578 m2
0 百万美元
[34390] Land affected within corridor of impact1 行 · 小计 —
项目(原文)
数量
金额
Land affected within corridor of impact2012 · Table Results of Resettlement
240924 m2
0 百万美元
[34390] Substation site area1 行 · 小计 —
项目(原文)
数量
金额
Substation site areaTakeo 32,416 + WPP 64,799 · 2012 · Table Results of Resettlement
97215 m2
0 百万美元
[34390] Number of affected trees1 行 · 小计 —
项目(原文)
数量
金额
Number of affected trees2012 · Table Results of Resettlement
31560 tree
0 百万美元
在同类电力项目中的位置
总投资
本项目 76
25.44中间值 4061.2
百万美元 · 灰点为同类项目,色带为常见范围
工期(批准 → 关账)
本项目 2
2中间值 36
年 · 灰点为同类项目,色带为常见范围
原文(7)
出资方Asian Development Bank
“m of 220 kV double-circuit
transmission line financed under the ADB loan would be built to transport electric power from
Viet Nam to Phnom Penh and nearby areas. The 220 kV was sel”
· 第 11 页地点Takeo
“TAKEO Ba Veal Renh Tani ssa Project Transmission Line Kampot cR Linking Project (by other)”
34390-013-cam-pcr.txt · 第 8 页电压等级230 kV
“19 1- Transmission Towers 230kV Line 20 Area of land for tower 2.24 21 Agricultural land Cat.A 0.60 3,600 2,160.00 22 Agricultural land Cat.B 0.70 5,400 3,780.00 23 Agricultural land Cat.C 1.00 1,575 1,575.00 24 Easement Area* (COI) 25 Agri…”
34390-01-cam-rp.txt · 第 4 页线路长度22 km
“Penh substation to General Substation (GS) 3 and stringing of conductors for about 22 km of 115 kV line to complete the second circuit between the three existing substations in Phnom Penh, known as GS1, GS2, and GS3”
34390-013-cam-pcr.txt · 第 12 页批准2010
“s Project Number: 34390 October 2010 Cambodia: Greater Mekong Subregion Transmission Project (Loan 2052-CAM) Prepared by: Electricite du Cambodge (EDC) with supported by Resettlement Department of the Ministry of Economy and Finance (RD/MEF…”
34390-01-cam-rp.txt · 第 1 页生效2005
“s signed on 10 November 2004, and the loan became effective on 25 March 2005”
34390-013-cam-pcr.txt · 第 14 页开工2007
“. Construction activities actually commenced in January 2007 and were completed in November 2011”